Master plans in Panama: what they include and in what order

A master plan is the overall design of a development: where the lots, streets, green areas and utilities go, in which phases it is built and why. In Panama it rests on studies of the site and, under the requirements of MIVIOT's One-Stop Window, a project of more than 10 hectares files its schematic design together with its approved land-use scheme (EOT).
What a master plan decides
The master plan organizes the whole site before each piece is designed. It sets the uses and their intensity: housing, retail, community facilities or recreation, and how many units fit without overloading roads or utilities. It lays out the road network, from the main access down to local streets, and divides it into blocks and lots. It sets aside green and public areas and decides what to keep from the landscape: streams, forest or slopes best left alone. It works out where drinking water comes from, where rainwater goes and where the sanitary sewer runs. And it splits the development into phases, so that each one works on its own while the next is built.
| Component | What it defines | What it rests on |
|---|---|---|
| Uses and densities | Housing, retail, facilities and recreation, and how many units the site allows | The land use assigned by the plan in force and the product to be developed |
| Road network | The access, main streets and local streets | Topography and the connection to existing roads |
| Lot layout | Blocks and lots, with their dimensions | Topography and the land-use rules |
| Green and public areas | Parks, recreation and what is kept from the landscape | Environmental and hydrological studies |
| Utilities | Drinking water, sanitary and storm sewers, and electricity | Hydrology, geotechnics and the public networks available |
| Phases | What is built first and how each phase works on its own | The developer's sales and investment plan |
Before drawing: the site
A master plan is only as good as what is known about the site. That is why it starts with a diagnosis: the legal status of the property at the Public Registry, its cadastral plan, the topography, the soil and how water behaves. Geotechnical studies tell where building is possible and on what foundations; hydrological studies, how the land drains and which areas flood. It is also necessary to know the land use assigned to the site. Law 6 of 2006 organizes planning in national, regional, local and partial plans; in the District of Panama the municipality's local plan applies (Agreement 61 of 2021, amended in 2025). If the assigned use does not allow the project, changing it is a separate procedure with its own studies, and it is worth knowing that before designing.
From master plan to land-use scheme
The master plan is the design document; before the authorities, a large development is filed as a land-use scheme (esquema de ordenamiento territorial, EOT). According to the requirements of MIVIOT's One-Stop Window, a project of more than 10 hectares files its schematic design together with the resolution of the Urban Development Directorate that approves the EOT. The plan then becomes a subdivision schematic design, reviewed at the same time by MIVIOT, MOP, MINSA, IDAAN, the Ministry of Environment and ATTT. The environmental impact study and the construction drawings come next. The full sequence, with what each agency asks for, is in the guide Land subdivision in Panama: steps and permits, in order.
An example: Woodlands, Panamá Pacífico
At Woodlands, Panamá Pacífico, in Arraiján, Consultores Urbanos Panamá did the master plan, the schematic design and the infrastructure design for 60 hectares. It is the design stretch of this guide in a single project: first the overall plan, then the schematic design, and finally the drawings for streets, water, sewers and drainage used to build it. When the master plan has already resolved slopes, drainage and access, the schematic design and the drawings start from decisions already made, not from scratch. In all, the firm has planned more than 2000 hectares since 1999.

How long it takes and what drives the cost
The time and cost of a master plan depend on four things: the size of the site, the information already available about it, whether the land use allows the project, and its environmental category. The review phase of the environmental study has caps set by Executive Decree 4 of 2026: up to 30, 80 or 120 business days for category I, II or III. Admission and the decision add to that, the clock stops while clarifications are answered, and preparing the study takes its own time. A site with up-to-date surveys and studies moves faster than one starting from scratch, and a land-use change can be the longest stretch of the road. That is why the first useful step is a diagnosis: with the location, the area and what is to be developed, it becomes clear which studies are missing and where to start.
Frequently asked questions
Are a master plan and a schematic design the same thing?
No. The master plan organizes the whole development and its phases. The subdivision schematic design is the formal filing at MIVIOT's One-Stop Window, where MIVIOT, MOP, MINSA, IDAAN, the Ministry of Environment and ATTT review it at the same time.
Does every project need a land-use scheme?
The One-Stop Window requires it for projects of more than 10 hectares: the schematic design is filed with the resolution approving the EOT. At any size, the design starts from the land use assigned by the plan in force.
How long does environmental review take?
Executive Decree 4 of 2026 sets up to 30 business days for category I, 80 for category II and 120 for category III. Those are the caps for the review phase: they do not include admission, the decision, pauses for clarifications or the time to prepare the study.
If you have land under evaluation, Consultores Urbanos Panamá handles the whole urban planning process, from the diagnosis and the master plan to the schematic design, and guides the permitting.
Sources
- Law 6 of 1 February 2006, regulating land-use planning for urban development (Official Gazette 25478, in Spanish)
- Executive Decree 4 of 28 May 2026, regulating environmental impact assessment (Ministry of Environment, Official Gazette 30534-B, in Spanish)
- MIVIOT (Ministry of Housing and Land Planning), One-Stop Window requirements for urbanizations and segregations (in Spanish)
- Municipality of Panama, Agreement 270 of 23 September 2025, amending the district's local land-use plan (Agreement 61 of 2021) for the corregimiento of San Francisco (Official Gazette 30388-A, 16 October 2025, in Spanish)
- Consultores Urbanos Panamá, portfolio published at cu-pa.com (October 2026)